Brown and Caldwell’s design to retrofit a 40 mgd wastewater treatment plant’s anaerobic digesters for the Columbus Water Works (CWW) used the first-of-its-kind Columbus Biosolids Flow-Though Thermophilic Treatment (CBFT3) process and cogeneration. CBFT3 converts the existing mesophilic digestion process to low-cost thermophilic digestion, produces Class-A biosolids, and reduces required batch processing times from an EPA-required 24 hours to 30 minutes, saving at least $3 million in capital costs. The new lean-burn engine generators produce 15 percent more power than previous generation engines or 60 percent more power than microturbines, with low exhaust emissions. This project is the first thermophilic anaerobic digestion project in the United States to be run entirely from heat generated from digester-gas-fueled power generation. Power generation has saved CWW as much as $19,000/week. The overall design produces a net carbon offset of 9,500 metric tons of CO2e emissions per year.
Awards
-
2008
International Water Association, Project Innovation Awards, Superior Achievement Award and Applied Research Winner
-
2007
American Council of Engineering Companies, Engineering Excellence Award
-
2005
American Council of Engineering Companies, National Honor Award
-
2005
American Council of Engineering Companies of Georgia, Grand Conceptor Award
Related Projects
Restoration with the future in mind
Building resilience through adaptive strategies
A history of delivering innovative and forward-thinking solutions
Establishing a vision to meet future water challenges
Colorado Water Treatment Plant Optimization Study
Big Creek Water Reclamation Facility
James R. DiIorio Water Reclamation Facility Ntensify™ Nutrient Removal
Southwestern Parkway Combined Sewer Overflow Basin
City of Memphis Industrial Discharge Smart Sensor Monitoring
Integrated Utility Data Interface for Water Quality Optimization
Pure Water San Diego
Southeast Plant Biosolids Digester Facilities
Greenfield Water Reclamation Plant Expansion
Kaneohe-Kailua Regional Wastewater Treatment Plant, Facilities Plan, Tunnel Influent Pump Station (TIPS)
Lake Oswego Interceptor Sewer
Process Water Reclamation Facility
New Class A Biosolids and Energy Facility at Blue Plains Advanced Wastewater Treatment Plant
40-Year Wet-Weather Management Plan
Bull Run Water Filtration Plant
MS4 Compliance in the Chesapeake Bay
Mine, Landfill, and Manufacturing Site Remediation Planning
Metals-Impacted Soil Remediation
Littleton/Englewood Wastewater Treatment Plant
Large Diameter Pipeline Design
Landfill Treatment Upgrade Feasibility Study
Landfill Expansion and Containment
Lake Townsend Raw Water Intake and Pumping Station
Lake Erie Water Intake and Pumping Station Process Optimization
Water Treatment Plant Expansion
Water Supply Study
Wastewater Plant Tertiary Treatment and Transmission Pipeline
Val Vista Water Main Rehabilitation
Ultrafiltration Technology Pilot Study
Trickling Filter/Solids Contact System Design and Implementation
Stormwater Infrastructure Improvements
Stormwater Control and Management
Stibnite Gold Mine Environmental Impact Statement and Historic Mining District Restoration
Shipyard Remediation and Redevelopment
RM Clayton Water Reclamation Center Headworks
Remediation at a Steel and Gas Manufacturing and Storage Site
Remediation at a Former Manufacturing Facility
Remedial Process Optimization
Regulatory Support and Environmental Compliance
Pure Water San Diego Potable Reuse Program
Program Management
Pressurized MIEX System Design
Pipeline Construction, Environmental Compliance, and Permitting
Ozone Water Treatment Plant Expansion
Ordot Landfill Closure
Oakley Station Separation Sewer Project
Nutrient TMDL Planning and Regulatory Compliance
North and South Complex Water Quality Improvements
North 27th Street Inline Storage System
Johns Creek Environmental Campus
Integrated Wet Weather Planning
Integrated Wet Weather Management
Infrastructure Replacement and Rehabilitation Planning
Infrastructure Renewal and Replacement Program
Industrial Spill Prevention, Control, and Countermeasures Plans
Industrial Reuse and Aquifer Replenishment Project
Indian Head Wastewater Treatment Plant Upgrades
Groundwater Flow and Transport Modeling
Greenfield Pre-Treatment Plant
Former Manufacturing Facility Site Remediation
Former Power Plant Remediation
Former Manufacturing Site Remediation
Force Main Inspection and Condition Assessment
Former Nuodex Site Remediation and Restoration
Express and Ground Operations Environmental Support
Environmental Restoration Program Optimization
Dixie Drain Phosphorus Removal Facility
Discharge Treatment Analysis
Development, Maintenance, and Audits of Environmental and Safety Management Systems
Denver Regional Transportation District’s Elati Light Rail Station
Groundwater Remedial Action Construction
Turnkey Excavation and Dewatering Design-Build
Coosa River Basin Nutrient Trading Framework
Comprehensive Manufacturing Environmental Health and Safety Program
Compliance and Permitting Program Management and Implementation
Compliance and Permitting Assessment
Companywide Environmental Health and Safety Program
Cogeneration System Upgrade
Coastal Master Plan
Climate Change Adaptation Planning
Chambers Creek Regional Wastewater Treatment Plant Expansion
Camp Pendleton Infrastructure Expansion
Biological Nutrient Removal Pilot Facility
Annacis Island and Lulu Island Wastewater Treatment Plants
American Cyanamid Superfund Site Remediation
Aggregate Mining Facility Remediation
Biosolids Management Program Upgrade
Related News
- BC Compliance News: November 2021 environmental regulations
- Solving the nutrient challenge at Pueblo, CO
- Ohio treatment plant upgrade could include innovative digestion process
- The Water Research Foundation and utilities collaborate to fund energy efficient nutrient management study
- Brown and Caldwell’s Natalie Sierra appointed vice chair of the Water Environment Federation’s Residuals and Biosolids Committee
- Hidden Beauty of The Water Cycle: An Interview with Photographer Brad Temkin
- Poop-derived fruits are known to grow in sewage plants
- City of Columbus selects Brown and Caldwell for pioneering wastewater acid digestion project
- MSU-led team receives nearly $2 million EPA grant to explore biosolid treatments, effects of chemical pollutants such as PFAS
- Haunted Waters